Part 3: Create Test Document With Test Design

II.  How to baseline version for a Test Document?

In order to baseline a version for a Test Document, a Test Design must be created before. That means Test Viewpoint, Function List and Test Matrix must have data.

This function can only be performed by PM and test leader

Step 1: Inside Test Document, select Sub Project, then click on [Baseline] button => popup Add New Version will be displayed.

Step 2: Inside the Add New Version popup, input the name of version into the text box.

Step 3: Click on [OK] button.

Baseline version will be created successfully and displayed as the Latest Baseline: